Ongoing story · Updated 5 Nov 2026
The Hua Hin beachfront demolition
How 26 buildings on public beach land between Hua Hin Fishing Pier and the Chao Mae Thap Thim Shrine came to face the bulldozers, and what happens next.
Timeline
-
2014
The Supreme Court orders the removal of structures on public land along the stretch, in cases involving 40 owners. Fourteen comply; 26 challenge the municipality’s orders and later lose at the Supreme Administrative Court.
Source -
18 Sept 2026
Hua Hin Municipality announces the clearance of buildings between the Fishing Pier and the Thap Thim Shrine, starting 25 September.
Source -
25 Sept 2026
A 120-day demolition contract starts, running to 22 January 2027. Officials begin visiting affected properties to explain the orders.
Source -
14 Oct 2026
Planning meeting with police, the Marine Department, land agencies and utilities. Phase one will target sea-facing extensions, signs and empty buildings.
Source -
16 Oct 2026
Planned start of demolition is postponed after the National Human Rights Commission asks for more time to talk.
Read our report → -
22 Oct 2026
After meeting officials, the NHRC says it will not interfere with the court orders. It received complaints from 19 residents.
Read our report → -
22 Oct 2026
Talks at the municipal office end without a deal. Residents decline to sign a proposal giving them until 22 November to say whether they will dismantle their buildings, and the mayor says the municipality will enforce the court order.
Read our report → -
29 Oct 2026
The municipality meets police, the electricity authority, the land office and the district to plan site work. The mayor says machinery starts the following week, Monday to Friday, with staged warnings for anyone who obstructs and criminal cases prepared against 26 people (15 municipal, 11 Marine Department). Utility agencies are to notify residents of their steps.
Read our report → -
30 Oct 2026
Machinery moves onto Naresdamri Road and the first building comes down after its owner agrees. Notices on locked doors give 20 November as the date for demolishing the other 14 municipal-case buildings. Owners say they are going to the civil court.
Read our report → -
31 Oct 2026
The pilot building, house no. 23 on Naresdamri Road, is more than 70 percent demolished. Recovered items are logged and stored at the municipal machinery depot on Soi Hua Hin 102; owners have 30 days to collect them before they go to public auction. Notices with the demolition date are posted on buildings whose owners have not cooperated.
Source -
2 Nov 2026 · Coming up
Municipality plans to start filing complaints at Hua Hin Police Station against owners for breaching the orders that ban use of the buildings and require demolition. It is also considering action on the further 11 structures originally budgeted for demolition by the port authority.
Source -
4 Nov 2026
Mayor Nopporn Wuttikul chairs a progress meeting on the 15 buildings. Legal officers report an owners’ appeal and a new lawsuit before the courts, letters to each owner are ordered, and staff are briefed for work on 6 November, starting with the parts that project over the sea.
Read our report → -
6 Nov 2026 · Coming up
Planned day of work on the beachfront. Two Thai reports mention this date, one as the expected finish (MGR Online, 31 October) and one as the day staff are briefed to work (Siamrath, 4 November).
Source -
20 Nov 2026 · Coming up
Municipality says it will begin demolishing the remaining 14 buildings, cutting locks if owners do not give access.
-
22 Jan 2027 · Coming up
Demolition contract ends. Concrete barriers are planned to stop the beach being reoccupied.