  1. 2014

    The Supreme Court orders the removal of structures on public land along the stretch, in cases involving 40 owners. Fourteen comply; 26 challenge the municipality’s orders and later lose at the Supreme Administrative Court.

    Source
  2. 18 Sept 2026

    Hua Hin Municipality announces the clearance of buildings between the Fishing Pier and the Thap Thim Shrine, starting 25 September.

    Source
  3. 25 Sept 2026

    A 120-day demolition contract starts, running to 22 January 2027. Officials begin visiting affected properties to explain the orders.

    Source
  4. 14 Oct 2026

    Planning meeting with police, the Marine Department, land agencies and utilities. Phase one will target sea-facing extensions, signs and empty buildings.

    Source
  5. 16 Oct 2026

    Planned start of demolition is postponed after the National Human Rights Commission asks for more time to talk.

    Read our report →
  6. 22 Oct 2026

    After meeting officials, the NHRC says it will not interfere with the court orders. It received complaints from 19 residents.

    Read our report →
  7. 29 Oct 2026 · Coming up

    Water and electricity to the affected buildings are due to be cut.

  8. 22 Jan 2027 · Coming up

    Demolition contract ends. Concrete barriers are planned to stop the beach being reoccupied.