M8 Motorway Through Hua Hin: Route, Interchanges and a 2037 Opening

The Department of Highways has picked a route for the M8 motorway between Cha-am and Pran Buri, with a Hua Hin interchange at Hin Lek Fai. Construction is pencilled in for 2033 and opening for 2037.

by Klaus · · 5 min read
A multi-lane motorway running between pine forest and grass verges under a blue sky (illustrative stock photo, not Thailand).
Photo: Robert Obrębski via Pexels
Link copied

A new four-lane motorway is planned to skirt Hua Hin on its western side, with an interchange at Hin Lek Fai, but the earliest opening in the plans is 2037. The Department of Highways showed the chosen route for the M8 section between Cha-am and Pran Buri at a public seminar on 25 November. The venue was the Suan Dusit University Hua Hin Education Centre. Banmuang reports that nearly 200 officials, community leaders and residents attended, with Prachuap Khiri Khan deputy governor Preeda Sukjai in the chair.

The department’s case is simple. It says the motorway would pull long-distance traffic out of Hua Hin and take pressure off Phetchakasem Road at rush hour and during holidays. The consultants are now reviewing the feasibility study and detailed design, and redoing the environmental impact assessment (EIA) to match today’s land use and economy.

The route, kilometre by kilometre

The preferred line runs about 61 kilometres. It starts in Wang Krai, Tha Yang district, Phetchaburi, and crosses into Prachuap Khiri Khan at Hin Lek Fai, in Hua Hin district. Banmuang says the line was bent away from a military security area at Ban Nong Suea Dam, following an army resolution. It then passes Thap Tai, running parallel to Highway 37 on its western side, and ends at kilometre 182+097 at Ban Wang Yao, Wang Phong subdistrict, Pran Buri.

For the Hua Hin to Pran Buri stretch, the department picked route option 1, which scored highest when compared on engineering, traffic, economics, investment and environmental effects. It would be a four-lane motorway on a right of way about 100 metres wide, with service roads where needed. The table lists the features Banmuang gives for the Prachuap Khiri Khan stretch.

FeatureLocationDetail
Hua Hin interchangeKm 158+400, Hin Lek FaiJoins Highway 3218, double trumpet design
Hua Hin rest areaKm 170+600, Thap TaiService stop for motorway users
Pran Buri interchangeKm 178+000, Wang PhongJoins Highway 37, double trumpet design
U-turnsHighway 3218Two
BridgesCrossings of highways and local roadsEight, so communities either side keep access

Promised versus now

Nobody should plan a commute around this yet. The department’s outline has survey, design and EIA work in 2026 and 2027, then EIA approval between 2028 and 2030. Land acquisition follows in 2031 and 2032, construction runs from 2033 to 2036, and opening is 2037, eleven years from today. Banmuang gives no cost for the Cha-am to Pran Buri section, and no toll rate, so we cannot say what a trip would cost.

The project’s history suggests caution. The first phase of the wider M8, from Nakhon Pathom to Pak Tho, was meant to start building in 2027, according to Bangkok Post in March 2025. Thansettakij reported at the time that it would open in 2031 at a cost of ฿61.154 billion. The Nation now reports a target of 2033, a ฿54.562 billion first-stage budget and civil works starting in 2028, with a Cabinet submission due by the end of 2026.

March 2025 planOctober 2026 plan
Nakhon Pathom to Pak Tho opening20312033
Construction start20272028
Budget฿61.154 billion in total฿54.562 billion for land and civil works

The budgets look different but are not. Thansettakij’s 2025 total includes ฿6.591 billion for systems, and the Nation says the same systems package sits on top of its ฿54.562 billion. Take it out and the two figures match, so the money has held steady while the calendar has slipped two years. The middle phase, Pak Tho to Cha-am, was described in 2025 as needing a new route study because of complaints from landowners in Phetchaburi, according to Thansettakij.

What residents asked for

The 25 November meeting was the second seminar. At the first public hearing on 10 June, held at a Hua Hin hotel, speakers asked that the project spare the Kaeng Krachan forest complex, Matichon Online reported, as summarised by Ground News. Banmuang’s account of the second meeting does not say what was asked this time. It says only that participants could put questions, which will feed into the EIA report.

The department will next hold a second small-group meeting on measures to prevent and reduce environmental damage with communities. Project information is on m8chaampranburi.com and on a Facebook page called “M8 ปากท่อ–ชะอำ”.

For a Hua Hin buyer or owner, the practical question is land. A right of way of 100 metres, plus interchanges at Hin Lek Fai and Wang Phong, will touch plots that are rural today. No source yet says how many rai or how many owners are affected, or when expropriation notices would arrive. Those answers should come with the EIA and the land acquisition plan, so anyone with land near Highway 3218 or Highway 37 should watch the project page rather than rely on rumour.