Ongoing story · Updated 27 Nov 2026
The M8 motorway and Hua Hin
The planned Nakhon Pathom to Pran Buri motorway would skirt Hua Hin on its western side. Here is how the plan, the route and the opening date have moved.
Timeline
-
27 Mar 2025
The transport minister says the first phase, Nakhon Pathom to Pak Tho, will begin building in 2027. Thansettakij reports a ฿61.154 billion total and an opening in 2031.
Source -
10 Jun 2026
First public hearing on the Cha-am to Pran Buri section at a Hua Hin hotel. Speakers ask that the project spare the Kaeng Krachan forest complex, according to Matichon Online.
Source -
24 Oct 2026
The Nation reports the first phase now targets a 2033 opening, a ฿54.562 billion land and civil works budget and civil construction from 2028, with a Cabinet submission due by the end of 2026.
Source -
25 Nov 2026
Second seminar on the Cha-am to Pran Buri section in Hua Hin shows the preferred 61 km route, with interchanges at Hin Lek Fai and Wang Phong. Opening is pencilled in for 2037.
Read our report → -
31 Dec 2026 · Coming up
Target for the Department of Highways to submit the first phase to the Cabinet. A second small-group meeting on environmental measures for the Cha-am to Pran Buri section is also planned, with no date given.